- PN07 -
Clay Street Reconstruction

Project Complete

Project Image
Map and information by Geauga County Deputy Engineer Shane Hajjar
Office of Joe Cattell, Geauga County Engineer
Project Name:
The Cement Stabilization and Asphalt Repaving of Sections H&I of Clay Street, CH 37
Contract Number:
RC-37HI-07
Location:
Montville and Thompson Townships, Geauga County
Construction Cost Estimate:
$615,000.00
Bid Date:
June 20, 2007
Low Bid:
$516,848.00
Contractor:
Ronyak Paving, Inc. from Burton, Ohio
 
Click Here To View Bid Tabulation
Final Contract Amount:
$530,273.75
Maintenance of Traffic:
Road will Be Closed to Thru Traffic. Detour Route: SR 86 - Hart Road
Project Description:
The existing roadbase will be cement stabilized and repaved with asphalt. The shoulders will be paved. This project will improve Clay Street between Hart Road (TR 63) and Plank Road (SR 86). The project will be funded with Local County Road and Bridge Levy funding.